Mihăilești – Solar Power Plant with Battery Energy Storage System in Romania**

First Major Investment Abroad

Date publishedNovember 27, 2026

The Mihăilești solar power plant and battery energy storage project in Romania is ENNA Group’s first major investment outside Croatia. The project marks an important step in ENNA Group’s international expansion and the development of its energy business across Central and South-Eastern Europe.

The solar power plant, with an installed capacity of 87.5 MWp, is being built at the Mihăilești site, 25 kilometres south-west of Bucharest, and will cover an area of 93 hectares. The project also includes a battery energy storage system (BESS) with a power output of 70 MW and a storage capacity of 140 MWh.

The total investment exceeds EUR 80 million. The project is being developed through the special-purpose vehicle PVP Cepheus by ENNA Solar, a member of ENNA Group responsible for the development and investment in renewable electricity generation facilities.

Construction of the solar power plant began in December 2025, following the signing of an EPC contract with Romanian company ENEVO Group, which is responsible for the engineering, procurement and construction of the facility on a turnkey basis.

The international verification and inspection company Bureau Veritas is providing expert supervision services in accordance with FIDIC standards, overseeing the inspection of equipment manufacturing and installation, and ensuring quality control throughout all stages of project implementation and the warranty period.

Throughout 2026, work progressed across all key components of the project. By the end of 2026, construction of the solar power plant is nearing completion, and the installation of the main 80 MVA power transformer, manufactured at KONČAR D&ST’s facility in Zagreb, has also been completed. The transformer is a key component of the infrastructure required to connect the power plant to the electricity grid.

At the same time, development of the battery energy storage system is progressing. Its design has been completed, and delivery of the equipment is expected in December 2026.

Commercial operation of the entire project is scheduled to begin in April 2027.

By combining a solar power plant with a large-scale battery energy storage system, the project enables not only the generation of renewable electricity but also its storage and more flexible management of electricity supplied to the grid. This increases the ability to adapt power generation to the needs of the electricity system and supports the integration of renewable energy sources.

Mihăilești marks an important step in ENNA Group’s international expansion and the development of its energy business across Central and South-Eastern Europe.